Document Type

Poster

Journal/Book Title/Conference

College of Engineering Senior Design Projects

Publisher

Utah State University

Location

Logan, UT

Publication Date

2019

Abstract

Laytona Subdivision, located in Layton, UT, currently uses traditional curb and gutter to transport storm runoff. This system is no longer adequate due to lack of slope and aging curb and gutter. Layton City will replace the current system with an underground storm drain system. Storm water runoff will be collected and transported to an existing detention pond.

Alternatives Three other alternative storm drain systems were considered for this project.

Cost Estimate The estimated cost of completion is $831,710.00.

Design Software To complete this project ASE used AutoCAD Civil 3D, Excel, and Autodesk Storm and Sanitary Analysis.

Design Standards All design was done in accordance to Layton City Storm Drainage Improvements Manual.

The design of the Laytona storm drain system was completed from January 2018 to April 2019. Aqua Solutions would like to thank our external Professional Engineers Ashley Thoman and Stephen Jackson and Faculty Advisor Blake Tullis.

Share

COinS