Abstract
XTO has requested their existing Temporary Use Permit (UTU-82322-01), which authorizes an existing 8 inch, surface, steel, and natural gas pipeline be converted to a permanent right-of-way grant. In addition, XTO proposes to remove a portion of the existing pipeline and to install an additional 15,075 feet of 12 inch, buried, natural gas pipe line to re-direct the flow of gas. XTO has constructed a natural gas compressor plant (Wild Horse Bench Compressor Site) on Ute Tribal land and would like to redirect the flow of gas from the Kings Canyon Area to this facility which involves the removal of a portion of pipeline and add an additional pipeline.
Recommended Citation
United States Department of the Interior, Bureau of Land Management, "Kings Canyon to Alger Pass Pipeline Project, Project No. UTU-82322" (2012). Environmental Assessments (UT). Paper 13.
https://digitalcommons.usu.edu/utah_enviroassess/13
Comments
Environmental Assessment UT-G010-2011-0120-EA