Abstract

Desilting basins play an important role in run-of-river hydro power projects on Himalayan Rivers. These rivers carry huge amount of sediment with them, due to steep slopes and fragile geology of the region. The suspended sediment enters through the power intake and ultimately the power house. This causes heavy damage to the turbines and other under water parts. Therefore, desilting basins are provided to eliminate suspended sediment from the water conductor system. The design of desilting basin is verified on a physical model for 90% removal of suspended sediment coarser than 0.2 or 0.3 mm and efficacy of flushing tunnel below in transporting the settled sediment. Central Water and Power Research Station, Pune has conducted physical model studies for desilting basin for various hydro power projects in India and neighbouring countries. One such study, Hydraulic model studies for desilting basin for 500 MW Teesta-VI Hydro Electric Project, Sikkim is presented in this paper. Various design parameters such as length of desilting basin, length and bed slope of inlet transition, outlet transition, size of silt flushing tunnel, size and spacing of openings connecting main basin with silt flushing tunnel etc. were tested during the model studies. The results in terms of settling efficiency for 0.3 mm size particles were obtained.

Share

COinS
 
Oct 26th, 12:00 AM

Model Studies for Desilting Basin for Teesta-VI H.E. Project, Sikkim – A Case Study

Desilting basins play an important role in run-of-river hydro power projects on Himalayan Rivers. These rivers carry huge amount of sediment with them, due to steep slopes and fragile geology of the region. The suspended sediment enters through the power intake and ultimately the power house. This causes heavy damage to the turbines and other under water parts. Therefore, desilting basins are provided to eliminate suspended sediment from the water conductor system. The design of desilting basin is verified on a physical model for 90% removal of suspended sediment coarser than 0.2 or 0.3 mm and efficacy of flushing tunnel below in transporting the settled sediment. Central Water and Power Research Station, Pune has conducted physical model studies for desilting basin for various hydro power projects in India and neighbouring countries. One such study, Hydraulic model studies for desilting basin for 500 MW Teesta-VI Hydro Electric Project, Sikkim is presented in this paper. Various design parameters such as length of desilting basin, length and bed slope of inlet transition, outlet transition, size of silt flushing tunnel, size and spacing of openings connecting main basin with silt flushing tunnel etc. were tested during the model studies. The results in terms of settling efficiency for 0.3 mm size particles were obtained.